Z Company makes custom motorboats. It incurred the following costs for the just-completed job B011. 500 pounds of direct materials were used at a cost per pound of $25. The job cost sheet indicates...


Z Company makes custom motorboats. It incurred the following costs for the just-completed job B011.


500 pounds of direct materials were used at a cost per pound of $25. The job cost sheet indicates that a


total of 90 direct labor-hours incurred on job B011. The workers were paid at a rate of $18 per hour. The


company applies overhead based on machine hours. At the beginning of the year, it was estimated that


the total amount of overhead would be $180,000 and a total of 30,000 machine hours would be incurred.


Job B011 required 150 machine hours.


Required: Determine the total cost assigned to Job B011