Your company completed the East Side subdivision. The costs are shown in Figure 11-4. The site concrete labor and outside lighting were done by subcontractors. The grading and excavation, sanitary sewer, water line, and storm drain were done by the company’s excavation crew. The company’s minimum profit and overhead markup is 15%. Determine the profit generated by the estimator, project management, and the excavation crew on this project.