You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and...


You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks.<br>a) Complete the product structure.<br>Alpha<br>D(2)<br>D(3)<br>

Extracted text: You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. a) Complete the product structure. Alpha D(2) D(3)