"You have signed a contract to build a garage for the Simpsons. You
will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?"ID Description Predecessor (time/ days)A Pour foundationnone3Berect frameA4CroofB4DwindowsB1EdoorsB1FelectricalB3Grough-in frameC,D,E,F 2Hdoor openerE,F1IpaintG,H2JcleanupI1