You have just assessed a project, involving an immediate cash outflow followed by a series of cash inflows over the next seven years, by deducing the NPV and the IRR. You have now discovered that you...








  • You have just assessed a project, involving an immediate cash outflow followed by a series of cash inflows over the next seven years, by deducing the NPV and the IRR.




  • You have now discovered that you have underestimated the discount rate. Correcting for the underestimation will have the following effects, relative your original deductions:





                   NPV                  IRR






A               reduce            no change


B            no change         no change


C             increase             reduce


D             increase            increase