You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. Which of the following tools and techniques will you employ to produce the outputs for this process?
A. Activity list, expert judgment, alternatives analysis, project management software, and bottom-up estimating
B. Activity list, expert judgment, published estimating data, and project management software
C. Expert judgment, alternatives analysis, published estimating data, project management software, and bottom-up estimating
D. Expert judgment, alternatives analysis, published estimating data, and bottom-up estimating