You are considering the following two mutually exclusive projects. Using the replacement chain approach and a cost of capital of 10%, calculate the NPV of Project A. (Round to nearest $) Project A...





You are considering the following two mutually exclusive projects. Using the replacement chain approach and a cost of capital of 10%, calculate the NPV of Project A. (Round to nearest $)











































Project A



Project B



Year



Cash Flow



Cash Flow



0



(20,000)



(20,000)



1



15,000



5,000



2



20,000



10,000



3





15,000



4





50,000