You are a project manager working for International Movie Unlimited (IMU). IMU practices phase sequencing and requires reviews and approvals of each phase before the next phase can begin. This process...




You are a project manager working for International Movie Unlimited (IMU). IMU practices


phase sequencing and requires reviews and approvals of each phase before the next


phase can begin. This process is known all of the following except for which one?


Process group


Stage gate


Phase review


Kill point