XYZ is considering a 3-yr project. The initial outlay is -$120,000, annual cash flow is $50,000 and the terminal cash flow is $10,000. The required rate of return (cost of capital) is 15%. The net...


XYZ is considering a 3-yr project. The initial outlay is -$120,000, annual cash flow is $50,000 and the terminal cash flow is $10,000. The required rate of return (cost of capital) is 15%. The net present value is $736.42. What if the annual cash flow increases to $51,000 instead? Re-calculate the NPV.