Wind turbines (Figure 8.26) have been the subject of many LCAs, most of them motivated by a wish to demonstrate that the turbine quickly pays back the energy and saves the carbon emissions associated with its construction.
a) An approximate bill of materials is available for a Gamesa 2-MW wind turbine installed in a Spanish wind farm. Use the CES Edu Eco-audit tool to assess the energy and carbon associated with the materials of the turbine, assuming virgin materials are used.
(b) If the turbine has a capacity factor of 25%, how long will it take to return the energy of the materials of which it is made?