Which of the following makes up the scope baseline? Group of answer choices The approved project scope statement The approved scope management plan and WBS The WBS, approved project scope statement,...




Which of the following makes up the scope baseline?
Group of answer choices
The approved project scope statement


The approved scope management plan and WBS


The WBS, approved project scope statement, and WBS dictionary


The approved scope management plan, the WBS, and the WBS dictionary


You are a project manager working on a new software product your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and, therefore, needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000, and it would take an act of Congress to get it increased. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project?


Group of answer choices


Budget


Scope


Time


Quality



You are in the process of translating project objectives into tangible deliverables and requirements. All of the following are techniques used in the product analysis tool and technique of the Define Scope process except which one?


Group of answer choices


Value engineering and value analysis


Product configuration and specification analysis


Systems analysis and systems engineering


Product breakdown and functional analysis


your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of a/an ___________________.


Group of answer choices


Constraint


Objective


Assumption


Requirement


Your project's primary constraint is quality. To make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools?


Group of answer choices


Reserve analysis


Analogous estimating


Three-point estimates


Parametric estimating


You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for its customers. Customers must register before being allowed to order wine over the Internet so that legal age can be established. You know that the module to verify registration must be written and tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following?


Group of answer choices


Preferential logic


Soft logic


Discretionary dependency


Hard logic


You are working on a project that requires resources with expertise in the areas of hospitality management and entertainment. You are preparing your project schedule network diagram and know that you will use only finish-to-start dependencies. Which of the following diagramming methods does this describe?


Group of answer choices


PDM


ADM


AON


Network template


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the weighted average or expected value?


Group of answer choices


54


66


60


30


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project to meet the federal grant application date. This is an example of ___________________.


Group of answer choices


crashing Your selection is incorrect 


fast tracking


resource leveling


adjusting the resource calendar