What is the net effect on a project's NPV, if it's salvage value in 10 years increases from $24126 to $48252? Assume the discount rate is 8%, the CCA rate is 14.1%, the tax rate is 25%, and the...

Be fast pleaseWhat is the net effect on a project's NPV, if it's<br>salvage value in 10 years increases from $24126 to<br>$48252? Assume the discount rate is 8%, the CCA<br>rate is 14.1%, the tax rate is 25%, and the half-year<br>rule applies.<br>a) $6734<br>b) $12520<br>c) $9393<br>d) $11262<br>e) $16860<br>

Extracted text: What is the net effect on a project's NPV, if it's salvage value in 10 years increases from $24126 to $48252? Assume the discount rate is 8%, the CCA rate is 14.1%, the tax rate is 25%, and the half-year rule applies. a) $6734 b) $12520 c) $9393 d) $11262 e) $16860