Using the source and destination information below, what is the cost in the initial solution using northwest corner rule? TO PROJECT PROJECT B PROJECT C PLANT FROM A САРАСITIES PLANT 1 $10 $4 $11 70...


Using the source and destination<br>information below, what is the cost<br>in the initial solution using northwest<br>corner rule?<br>TO<br>PROJECT<br>PROJECT<br>B<br>PROJECT<br>C<br>PLANT<br>FROM<br>A<br>САРАСITIES<br>PLANT 1<br>$10<br>$4<br>$11<br>70<br>PLANT 2<br>$12<br>$5<br>$8<br>50<br>PLANT 3<br>$9<br>$7<br>$6<br>30<br>PROJECT<br>REQUIREMENTS<br>40<br>50<br>60<br>150<br>

Extracted text: Using the source and destination information below, what is the cost in the initial solution using northwest corner rule? TO PROJECT PROJECT B PROJECT C PLANT FROM A САРАСITIES PLANT 1 $10 $4 $11 70 PLANT 2 $12 $5 $8 50 PLANT 3 $9 $7 $6 30 PROJECT REQUIREMENTS 40 50 60 150