Using the priority list T3, T1, T6, T2, T5, T4, T7, schedule the project below with two processors. TI (3) T4 (11) T6 (5) End T2 (8) T5 (7) 17 (12) T3 (4) Task 5 is done by Select an answer starting...


Using the priority list T3, T1, T6, T2, T5, T4, T7, schedule the project below with two processors.<br>TI (3)<br>T4 (11)<br>T6 (5)<br>End<br>T2 (8)<br>T5 (7)<br>17 (12)<br>T3 (4)<br>Task 5 is done by Select an answer<br>starting at time<br>Task 7 is done by Select an answer e starting at time<br>

Extracted text: Using the priority list T3, T1, T6, T2, T5, T4, T7, schedule the project below with two processors. TI (3) T4 (11) T6 (5) End T2 (8) T5 (7) 17 (12) T3 (4) Task 5 is done by Select an answer starting at time Task 7 is done by Select an answer e starting at time