Using the information in Table 12-7, construct a PERT network and answer each of the following questions: a. What is the expected project completion data? b. What is the scheduled start and completion...

1 answer below »

Using the information in Table 12-7, construct a PERT network and answer


each of the following questions:


a. What is the expected project completion data?


b. What is the scheduled start and completion date for each activity?


c. Which activities are on the critical path?


d. How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?




Answered Same DayDec 25, 2021

Answer To: Using the information in Table 12-7, construct a PERT network and answer each of the following...

David answered on Dec 25 2021
120 Votes
1
PERT NETWORK
Given data
Respective table required for PERT network is shown below:
Notatio
ns:
E = Earliest occurrence time for the respective event
L =Latest allowable time for the occurrence of the respective event
ES = E of the tail event
EF = ES + Activity duration
2
LF = L of the head event
LS = LF – Activity duration ...