On January 3, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order:
1. Calculate the delivery cycle time.
a. 14.25 days
b. 13.75 days
c. 9.25 days
d. 5 days
2. Calculate the manufacturing cycle time.
a. 7 days
b. 12 days
c. 6.75 days
d. 3.5 days
3. Calculate the manufacturing cycle efficiency.
a. 100%
b. 29%
c. 33%
d. 50%