Use the following information to answer questions 1–3: On January 3, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order: 1. Calculate the...

Use the following information to answer questions 1–3:

On January 3, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order:


1. Calculate the delivery cycle time.


a. 14.25 days


b. 13.75 days


c. 9.25 days


d. 5 days


2. Calculate the manufacturing cycle time.


a. 7 days


b. 12 days


c. 6.75 days


d. 3.5 days


3. Calculate the manufacturing cycle efficiency.


a. 100%


b. 29%


c. 33%


d. 50%