Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 30 days.[5] My roll numbe 51572 mobile lasat digit 8 sibling 3 x: is a last digit of your roll...




  • Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 30 days.[5]


My roll numbe 51572


mobile lasat digit 8


sibling 3



                     x: is a last digit of your roll number



                       y: is a # of sibilings (0,1…….)



                        z: is a last digit of your mobile number













































































Activity





predecessors





Optimistic




Most likely




Pessimistic




A




-




5




6




8




B




-




3




4




5




C




A




2




3




4




D




B




x-1




x +4




x+6




E




B




1




3




4




F




-




1




10 -z+x




15-z+x




G




E,F




2




3




4




H




C,D




2+y




2+y




2+y




I




G, H




3




4




5




Jun 02, 2022