Use a one-way data table to see how sensitive the project completion time in the LAN project is to the duration of activity D (selecting software). Let the duration vary from 10 to 16 days in...


Use a one-way data table to see how sensitive the project completion time in the LAN project is to the duration of activity D (selecting software). Let the duration vary from 10 to 16 days in increments of 1 day.


Repeat the previous problem, but now keep track of the following outputs in your data table: the project completion time and the slack for each activity. As the duration of activity D changes, do any critical activities become noncritical? Do any noncritical activities become critical?