Under a unit-price contract with a 25 percent guarantee requirement of all unit prices quoted, the engineer’s estimate of earthwork quantities totals 9,270 cubic meters. If the actual quantities measured in the field for pay
purposes total 10,650 cubic meters, is a change order justified for the quantity change?