u) Project P rcquires an mycsiment of $95,000 and is expected to produce cash inflow of $20,000 per ycar for 8 years. The cost of capital is 11% Required: a) Pay-back period b) NPV c) PI d) IRR Should...


u) Project P rcquires an mycsiment of $95,000 and is expected to produce cash inflow<br>of $20,000 per ycar for 8 years. The cost of capital is 11%<br>Required:<br>a) Pay-back period<br>b) NPV<br>c) PI<br>d) IRR<br>Should you acccpt the project? Why or why not?<br>

Extracted text: u) Project P rcquires an mycsiment of $95,000 and is expected to produce cash inflow of $20,000 per ycar for 8 years. The cost of capital is 11% Required: a) Pay-back period b) NPV c) PI d) IRR Should you acccpt the project? Why or why not?