TITLE OF EXPERIMENT/EXERCISE: Project Planning and Scheduling Q1: Consider the following table summarizing the details of a project. Activity Predecessor Time(Weeks) 1 7 10 3 1 6. 4 2 5 4 6. 3,4 3 7...

I need the answer as soon as possibleTITLE OF EXPERIMENT/EXERCISE: Project Planning and Scheduling<br>Q1: Consider the following table summarizing the details of a project.<br>Activity<br>Predecessor<br>Time(Weeks)<br>1<br>7<br>10<br>3<br>1<br>6.<br>4<br>2<br>5<br>4<br>6.<br>3,4<br>3<br>7<br>5,6<br>a) Construct the Project network.<br>b) Find the Critical Path<br>

Extracted text: TITLE OF EXPERIMENT/EXERCISE: Project Planning and Scheduling Q1: Consider the following table summarizing the details of a project. Activity Predecessor Time(Weeks) 1 7 10 3 1 6. 4 2 5 4 6. 3,4 3 7 5,6 a) Construct the Project network. b) Find the Critical Path