WEBVTT 00:02:11.000 --> 00:02:11.900 all good 00:03:32.000 --> 00:03:32.900 Has the session started, I can't hear anything. 00:03:47.000 --> 00:03:47.900 yes it started 00:05:10.000 --> 00:05:10.900...

1 answer below »

View more »
Answered Same DayMay 15, 2021ACC00716Southern Cross University

Answer To: WEBVTT 00:02:11.000 --> 00:02:11.900 all good 00:03:32.000 --> 00:03:32.900 Has the session started,...

Aklank answered on May 18 2021
164 Votes
NPV is the easiest tool available to analyze the projects. If the NPV is positive, project will be accepted and if the NPV is negative, project will be rejected. For discounting all future cash flows, required rate of return will be used.
Major steps are taken to do NPV analysis as below:
· Calculation of revenues of the firm.
· Calculations of contribution margin by deduction of variable cost after adjusting the changes due to new scenario.
· Calculation of depreciation of the initial investment according to the feasible method.
· Calculation of net profit after taxes. Some cases net profit are treated as cash flows
· Estimating free cash for of the projects.
· Calculating the present value of cash flows using the discount rate given.
· Calculation on NPV by summing all present cash flows.
· Making the investing decision using the NPV rule to invest in the project if NPV>0.
Differential risk can be incorporated into NPV analysis by increasing the discount rate for projects with higher risk factor. This will reduce the present value of cash inflows, therefore increasing risk & uncertainty. In addition, the cash flows can be decreased by introducing a percentage of "Uncollectibles" - for example, introducing an assumption that 2% of cash benefits will be uncollectible, will reduce the cash inflows present value.
If the projects under evaluation fall in different risk class, then discount rate used to calculate NPV is different for all projects. The discount rate is adjusted on the basis of inherent risk of the projects. Discount rate is increased if risk...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30