The total investment required for a project is estimated at OMR 90, 000. The cash flows expected from the project for the first four years are given below. Year Project A Year 1 18,000 Year 2 28,500...

The total investment required for a project is estimated at OMR 90, 000. The cash flows expected from the project for the first four years are given below. Year Project A Year 1 18,000 Year 2 28,500 Year 3 42,000 Year 4 48,000 What will be pay back period? a. 3.03 b. 2.86 c. 2.63 d. All the options are wrong e. 3.23