The time to assemble the first unit on a production line is 6 hours The learming rate is 0 86. Approximately how long wilttake for the seventh unit to be assembled? The number of hours needed for the...


The time to assemble the first unit on a production line is 6 hours The learming rate is 0 86. Approximately how long wilttake for the seventh unit to be assembled?<br>The number of hours needed for the seventh unit to be assembled is hours (Round to one decimal place)<br>nswer in the answer box<br>

Extracted text: The time to assemble the first unit on a production line is 6 hours The learming rate is 0 86. Approximately how long wilttake for the seventh unit to be assembled? The number of hours needed for the seventh unit to be assembled is hours (Round to one decimal place) nswer in the answer box