The time taken for a particular operation for operator X in the Process Division of a manufacturing concern on three different counts was 24, 22 and 27 minutes while that of operator Y was 20, 23 and...


The time taken for a particular operation for operator X in the Process Division of a manufacturing concern on three different counts was 24, 22 and 27 minutes while that of operator Y was 20, 23 and 26 minutes. It has been ascertained that the rating of ‘X’ is 70/60 and that of ‘Y’ is 55/60. Allowance for fatigue, personal needs are assumed at 15 per cent. Calculate, using the above information as a base, for that particular operation, (i) the standard time, and (ii) the time allowed under an incentive allowance of 30 per cent of standard time.



Dec 18, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here