The student is to write a 1200-word essay addressing the following questions and to be submitted to GPM Program Coordinator within 7 working days after dissemination of this assessment instruction.1. Explain sequencing activities including the precedence diagram method. How do different relationships influence project scheduling? Provide examples of relationship that can be observed from the given case study.2. Create a simple schedule network diagram of the given case study. Discuss how changes in project activities can affect the project critical path(s).3. Explain how the project cost can be estimated. Apply appropriate estimating techniques to the given case study.4. Identify elements of cost that could incur in the case study and how they are classified.