PRO100_Assessment 2_Brief Page 1 of 6 ASSESSMENT 2 BRIEF Subject Code and Title PRO100 Information Systems Project Management Assessment Consultative Report Individual/Group Individual Length 1500...

1 answer below »
The question and case study and the file required for this is attached


PRO100_Assessment 2_Brief Page 1 of 6 ASSESSMENT 2 BRIEF Subject Code and Title PRO100 Information Systems Project Management Assessment Consultative Report Individual/Group Individual Length 1500 words Learning Outcomes The Subject Learning Outcomes demonstrated by successful completion of the task below include: a) Generate recommendations for information systems project planning b) Apply Project Management concepts to contemporary industry settings Submission Due by 11:55pm AEST Sunday end of Module 4.2 (Week 8) Weighting 40% Total Marks 100 marks Task Summary In this assessment, you will study a project case and develop a project schedule for that project. You are required to answer questions related to project risk management, communication management and the project duration reduction technique. Context: In response to the case study provided, write a consultative report focusing on the various processes in project knowledge areas, including the management of project schedule, cost, risk and resources. This assessment requires you to apply various tools and techniques you have learnt in management of project schedule, cost, risk and resources into a real-life case scenario. You will be presented with a case study, for which you assume the role of the project manager. You will be asked to go through a number of processes in the project knowledge areas above and generate outputs (some subsidiary plans of a project management plan) for those processes. This assessment provides you with an opportunity to view various processes in the planning process as a whole and develop an appreciation of schedule-cost-scope-risk trade-off. Instructions: Please read the attached Assessment 2_Case Study_ABC University. You are required to complete the following tasks during Professor Smith’s leave. Task 1 (15 marks) PRO100_Assessment 2_Brief Page 2 of 6  Create a new ProjectLibre file, name it “Task 1”;  Set the start date of the project; (1 mark)  Enter an appropriate title for this project; (1 mark)  Set all tasks to be auto-scheduled; (1 mark)  Enter the public holidays in the ProjectLibre file; (1 mark)  Enter all the activities in this project preserving the hierarchy of the WBS; (2 marks)  Make sure that the project title appears as the overall project summary at top of the activities list. It must appear as task 0 with WBS number 0; (1 mark)  Enter all milestones at the end of the task list; (1 mark)  Enter task durations assuming that ONLY ONE of each type of the required resource would be allocated to the task for now unless the task has a fixed duration. (2marks)  Add a “WBS Predecessors” column after the “Task Name”. (1 marks)  Enter all the predecessor information for each task and milestone. (1 mark)  Highlight the critical path. (1 mark)  Create a new Microsoft Word file, and name it “ABCU Project Report.docx”. This document will be referred to as “the Word document” in the following tasks.  In the Word document, report the critical path as shown in Task 1 at this stage. (1 mark)  Allocate the required resources to each task in the schedule. For Task 1, allocate only 100% of each resource to a task unless the task has a fixed duration. Please do not resolve resource over-allocation issues at this stage. (1 mark)  In the Word document, report the duration as well as the end date of this project as shown in Task 1 at this stage. Task 2 (10 marks)  Duplicate “Task 1” and name it “Task 2”. You should have two files saved: “Task 1” and “Task 2”. Complete Task 2 requirements in “Task 2”.  Allocate 300% of SD to activity 4.3 assuming that the total amount of work measured in “person-week” is unchanged. (1 mark)  In the Word document, report the duration as well as the end date of this project post the previous change. Report whether the additional resources allocated to activity 4.3 resulted in any changes in the duration of activity 4.3. Why or why not? Do the additional resources always result in a reduction of the activity to which the additional resources are allocated? Critically explain why or why not. (3 mark)  Resolve resource over-allocation issues (if any). For this project, do not “split tasks” and do not allow levelling to “adjust invidious assignments on a task”. (2 marks)  In the Word document, report in detail how you resolved resource over-allocation issues in ProjectLibre. Compare the duration and the end date prior and post resolving resource over- allocation issues. Critically explain why there has or has not been a change. (4 marks)  Save “Task 2”. PRO100_Assessment 2_Brief Page 3 of 6 Task 3 (20 marks) In a Word document, write a brief memo to the Pro Vice Chancellor of ABCU, informing him of the following information:  The completion date and the duration of this project. (1 mark)  The estimated direct labour costs for each resource. Present that information in a table. (3 marks) Resource Name Cost Requirement Engineer Business Analyst Software Architect Software Developer Software Tester Technical Document Writer Technical Support and Trainer  The major risks in this project. Present at least three threats (negative risks) and two opportunities (positive risks) in a table. (15 marks = each cell in the table worth 0.5 marks) Type Risk Description Owner Likelihood Impact Response type Treatment strategy Threat Threat Threat Opportunity Opportunity  Correct memo format (1 mark) Task 4 (15 marks) In the Word document, outline at least two strategies that can be used to reduce the duration of this project by two weeks, and the impact on project scope, cost and risk. The total word count should not exceed 400 words. However, you need to be specific about your strategy. For example, “reduce duration of activity 3.1” is not regarded as specific. Why would you choose that particular activity or activities among all the activities? How you would go about reducing the duration of that activity? Task 5 (20 marks) The enrolment officers and students are two important groups of stakeholders in this project. In the Word document, report the following:  What are the communication methods (pull or push) you would use to communicate to either of these two groups of stakeholders? (5 marks)  At the commencement of this project, does either of these two groups of stakeholders need to be notified of the commencement of this project? If so, draft an email for the Pro Vice Chancellor of ABCU to communicate that to the stakeholder. If not, justify why that PRO100_Assessment 2_Brief Page 4 of 6 stakeholder should not be notified. Your answer for this part should not exceed 150 words . (7 marks)  Upon ABCU accepting the end product (i.e. the online enrolment system), does either of these two groups of stakeholders need to be notified of the status of the project at this stage? If so, draft an email for the Pro Vice Chancellor of ABCU to communicate to that stakeholder. If not, justify why that stakeholder should not be notified. Your answer for this part should not exceed 150 words. (8 marks) Referencing It is essential that you use appropriate APA style for citing and referencing research. Please see more information on referencing here: http://library.laureate.net.au/research_skills/referencing Submission Instructions submit a Microsoft Word document (.doc or .docx) and TWO ProjectLibre files via the Assessment 2 section found in the main navigation menu of the subject Blackboard site. The Learning Facilitator will provide feedback via the Grade Centre in the LMS portal. Feedback can be viewed in My Grades. http://library.laureate.net.au/research_skills/referencing PRO100_Assessment 2_Brief_Final.Docx Page 6 of 6 Learning Rubric: Assessment Two Assessment Attributes Fail (Unacceptable) 0-49% Pass (Functional) 50-64% Credit (Proficient) 65-74% Distinction (Advanced) 75 -84% High Distinction (Exceptional) 85-100% Knowledge and understanding (Task 1–5) Consultative report focuses on various processes in project knowledge areas. Application of various tools and techniques in management of projects schedule, cost, risk and resources Lack of understanding of required concepts and knowledge of various processes in project knowledge areas. Key components of the assignment are not addressed. Lack of application of tools and techniques in management of projects schedule, cost, risk and resources. Limited understanding of required concepts and knowledge of various processes in project knowledge areas. Key components of the assignment are partially addressed with l imited application of tools and techniques in management of projects schedule, cost, risk and resources. An adequate understanding of the various processes in project knowledge areas. All key components of the assignment are addressed with an adequate level of application of the tools and techniques in management of project schedule, cost, risk and resources. A thorough understanding of the various processes in project knowledge areas. All key components of the assignment are addressed. Well demonstrated capacity to explain and apply relevant tools and techniques in management of project schedule, cost, risk and resources. An exceptional understanding of the various processes in project knowledge areas. All key components of the assignment are addressed. Demonstrates mastery of concepts and application of relevant tools and techniques in management of project schedule, cost, risk and resources to the case scenario. 80% Use of academic and discipline conventions Spelling, grammar, sentence construction, appropriate use of credible resources, Correct citation of key resources using APA
Answered Same DayMay 09, 2021PRO100Torrens University Australia

Answer To: PRO100_Assessment 2_Brief Page 1 of 6 ASSESSMENT 2 BRIEF Subject Code and Title PRO100 Information...

Amar answered on May 10 2021
146 Votes
1
Running Header: ABCU Project Report
2
ABCU Project Report
ABCU Project Report

Task 1
Critical path is presented as follows (highlighted in red) –
Figure 1 – Task 1 Critical Path (Screenshot from ProjectLibre file)
Total Duration: 287 days
End Date: 09th August 2021
Task 2
Duration: 287 da
ys
End date: 09th August 2021
The additional resources added to the task 4.3 did not lead to any change in the duration as well as end date. Change in resources do not always necessarily lead to changes in duration. In this case as task 4.3 is not part of the critical path, the additional resources to this task while reducing the duration of this specific task did not lead to any changes in the project duration / end date.
There no resource overallocation issue as the duration has been allocated considering the resource availability at hand.
Task 3
Memo to Pro Vice Chancellor, ABCU
Recipient:
Mr. X, Pro Vice Chancellor at ABCU
Subject: Memo on Project Planning Outcome
The detailed planning of the project processes has been completed. On the basis of the schedule estimation and planning, the duration as well as the end date of the project is as follows –
· Total Duration: 287 days
· End Date: 09th August 2021
The estimated resource cost is presented as follows –
Table 1 – Resource Cost
    Resource Name
    Cost $
    Requirement Engineer
     23,520
    Business Analyst
     59,920
    Software Architect
     75,600
    Software Developer
     181,440
    Software Tester
     72,800
    Technical Document Writer
     13,440
    Technical Support and Trainer
     17,640
     
     4,44,360
The major risks of the project are as follows –
Table 2 – Risk Assessment
    Type
    Risk Description
    Owner
    Likelihood
    Impact
    Response Type
    Treatment Strategy
    Threat
    Ineffective and inefficient planning / controls on account of lack of qualification and experience of the project manager leading to expenses being more than planned budget
    Project Manager
    Medium
    Medium
    Risk Reduction
    Undertake detailed process planning for the project, establish robust project controls and appoint experienced project manager
    Threat
    Ineffective and inefficient planning / controls on account of lack of qualification and experience of the project manager leading to delay in the planned project schedule
    Project Manager
    Medium
    Medium
    Risk Reduction
    Undertake detailed process planning for the project, establish robust project controls and appoint experienced project manager
    Threat
    A lack of clarity and definiteness in the overall communication planning leading to miscommunications as well as conflicts among the team members
    Project Manager
    Medium
    Medium
    Risk Reduction
    Undertake detailed planning for the communication process, and establish robust project controls for the communication plan in the project
    Opportunity
    Due to effective planning and increased productivity from project resources by avoiding resource resolution project is completed on...