A. What is the AC?
B. What is the PV?
C. What is the EAC? What does this mean?
D. What is the estimated time to completion? What does this mean?
E. Briefly discuss the output. Are you over/under budget? Are you ahead/behind schedule
A. What is the CV and SV? What is the CPI and SPI?
B. Assuming this trend continues, what is the project’s estimate at completion (EAC)?
C. Assume the current variances are atypical and that the remaining work will be completed using the original estimates. What is the project’s estimate at completion (EAC)?
D. EXTRA CREDIT: Assume the remaining work will be impacted by both the current cost and schedule. What is the project’s estimate at completion (EAC)?
Please make sure your submission clearly presents both the formula you used, your numerical answer and your answers to the questions. A Word file or a PDF of handwritten work are fine. If you use Excel, please make sure you have labeled everything clearly and professionally.