The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third month the EV = $50,000 and a SPI of 1.1 and CPI of 1.2. A. What is the AC? B. What is...

1 answer below »


  • The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third month the EV = $50,000 and a SPI of 1.1 and CPI of 1.2.


A. What is the AC?


B. What is the PV?


C. What is the EAC? What does this mean?


D. What is the estimated time to completion? What does this mean?


E. Briefly discuss the output. Are you over/under budget? Are you ahead/behind schedule




  • The earned value on your project is $280. The actual cost is $350. The planned value = $260. The total project budget is $500.


A. What is the CV and SV? What is the CPI and SPI?


B. Assuming this trend continues, what is the project’s estimate at completion (EAC)?


C. Assume the current variances are atypical and that the remaining work will be completed using the original estimates. What is the project’s estimate at completion (EAC)?


D. EXTRA CREDIT: Assume the remaining work will be impacted by both the current cost and schedule. What is the project’s estimate at completion (EAC)?



Please make sure your submission clearly presents both the formula you used, your numerical answer and your answers to the questions. A Word file or a PDF of handwritten work are fine. If you use Excel, please make sure you have labeled everything clearly and professionally.









Answered Same DayMay 27, 2022

Answer To: The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end...

Sandeep answered on May 27 2022
90 Votes
Sheet1
        Budget at Completion cost (BAC)     $200,000
        Original Time estimate to complete(months)    12

        Earned Value (EV)    $50,000
        Scheduled Performance Index (SPI)    1.1
        Cost Performance Index (CPI)    1.2
    A    What is Actual Cost (AC)    CPI = EV/AC
        AC    EV/CPI
        AC    $41,667
    Ans A    Actual Cost (AC)    $41,667
    B    What is Planned Value (PV)?
        SPI    EV/PV
        PV    EV/SPI
        PV    $45,455
    Ans B    Planned Value (PV)    $45,455
    C    What is Estimate at Completion (EAC)?
        EAC    BAC/CPI
        EAC    $166,667
    Ans C    Estimate at Completion (EAC)    $166,667
    D    What is the estimated time to completion? What does this mean?
        Estimated time to...