The managing partner of the Scott Corey accounting firm has decided that the system must be up and running in 16 weeks. Consequently, information about crashing the project was put together and is...

1 answer below »
The managing partner of the Scott Corey accounting firm has decided that the system must be up and running in 16 weeks. Consequently, information about crashing the project was put together and is shown in the following table:




(a) If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? What is the total cost of this?

(b) List all the paths in this network. After the crashing in part (a) has been done, what is the time required for each path? If the project completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this byinspection.

Answered Same DayDec 24, 2021

Answer To: The managing partner of the Scott Corey accounting firm has decided that the system must be up and...

David answered on Dec 24 2021
118 Votes
(a) Crash cost per week = (Crash Cost-Normal Cost)/(Normal time- Crash Time)
This is filled in las
t column.
(b) Also lowest Crash cost per week on Critical Path is Activity G at 700 per week. SO G should
be crashed.
Total Project cost after Crashing is Total Normal cost + Crash cost = 69500+...