Extracted text: The Labor Crew shown below is taken from the Building Construction Cost Database (BCCD) of R.S. Means. The crew produces 150 sq. ft of Stone Veneer per day. Material cost of Stone Veneer is $5.00 per sq. ft. Incl. Subs o& P Cost Per Man-hour Crew No. Bare Costs Bare Costs incl. O&P Crew D-10 1 Bricklayer Foreman 1 Bricklayer Hr. Daily $24.15 $193.20 $36.05 $288.40 177 20 Hr. Daily 22.15 33.05 264.40 2 Bricklayer Helpers 1725 276.00 25.75 412.00 1 Equip. Oper. (crane) 1 Truck Crane, 12.5 Ton 22.90 183.20 34.20 273.60 397.00 436.70 Daily Totals If each worker in the crew works 5 days a week, what are: a) Amount of Labor workhours in a week b) Weekly Bare Costs of Labor Costs per workhour for Equipment (including Overhead and Profit) d) Cost per workhour for Labor (including Overhead and Profit) e) Labor plus Material cost per sq. ft of Stone Veneer (including Overhead and Profit)