The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. Draw the network diagram for the...


The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis.


Draw the network diagram for the project below.


What is the critical path and completion time for the project?


Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
















































































Activity




Normal Time




Crash Time




Normal Cost




Crash Cost




Predecessor



A



10



7



2,000



2,600





B



12



8



1,500



2,000



A



C



16



12



2,200



3,000



A



D



8



7



2,500



3,000



B



E



12



9



1,950



2,275



C



F



9



8



800



1,000



D



G



24



19



3,650



4,000



E, F



H



17



14



1,200



1,800



G



Describe the difference between a fixed-quantity and a fixed-period inventory system?



Jun 10, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here