The following are the cash flows of two projects: Year Project A Project B 0 $ (400 ) $ (400 ) 1 230 300 2 230 300 3 230 300 4 230 a. Calculate the NPV for both projects if the discount rate is 10%....








The following are the cash flows of two projects:



























































YearProject AProject B
0$(400)$(400)
1230300
2230300
3230300
4230



a.Calculate the NPV for both projects if the discount rate is 10%.
(Do not round intermediate calculations. Round your answers to 2 decimal places.)








b.Suppose that you can choose only one of these projects. Which would you choose?








  • Project B







  • Project A







  • Neither