The details of a 12-hour volume study for a 4-leg road junction are tabulated below. The N-S major road has two through lanes on each approach while the E-W minor road has one through lane on each approach. Examine the fulfilment of traffic signal Warrants 1 (Condition B) using the .MUTCD 2009 standards Major Rd. (Total | Minor Rd. (Higher Start of approaches) approach) .a O W1B is not met .b o W1B is met
Extracted text: The details of a 12-hour volume study for a 4-leg road junction are tabulated below. The N-S major road has two through lanes on each approach while the E-W minor road has one through lane on each approach. Examine the fulfilment of traffic signal Warrants 1 (Condition B) using the .MUTCD 2009 standards Major Rd. (Total Minor Rd. (Higher of approaches) Hour Start approach) Hr 1 734 98 Hr 2 880 122 Hr 3 850 120 Hr 4 955 100 Hr 5 941 105 Hr 6 915 95 Hr 7 1040 140 Hr 8 1010 150 Hr 9 790 156 .a W1B is not met .b W1B is met