The company Sudbury Deck Builder wants to bid for a job to build a deck.Here are the job details:
1) Materials to do the Job:
2) Direct labour hours - 30 hours at $34/hour;
3) Direct overhead - $1,725
3) Administrative overhead - 10% of total direct costs;
4) Expected profit - 20% on top of total costs.
What is the total direct cost?
Already registered? Login
Not Account? Sign up
Enter your email address to reset your password
Back to Login? Click here