The company Sudbury Deck Builder wants to bid for a job to build a deck.Here are the job details:
1) Materials to do the Job:
2) Direct labour hours - 30 hours at $34/hour;
3) Direct overhead - $1,725
3) Administrative overhead - 10% of total direct costs;
4) Expected profit - 20% on top of total costs.
What is the total direct cost?
What's the total cost to build a deck (including G&A overhead)?
What should be the total bid for the deck project considering that Sudbury Deck Building wants 20% profit?