The Company is to submit a bid on the production of 10,000 ceramic salad bowls. It is estimated that the cost of materials will be $7,500 and direct labor, $ 10,100. Factory overhead is applied at $5...


The Company is to submit a bid on the production of 10,000 ceramic salad bowls. It is estimated that the cost of materials will be $7,500 and direct labor, $ 10,100. Factory overhead is applied at $5 per direct labor hour in the Molding Department and at 120% of the direct labor cost in the finishing Department. It is estimated that 800 direct labor hours will be required in Molding and the direct labor cost in Finishing will be $ 4,300. The company wishes a bid price consisting of a markup of 40% of its total production costs. Find estimated cost to produce, estimated prime cost, estimated conversion cost and Bid price?