The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: Performance Time...


Can you assist me with this question17  by showing me the process step by step so, I  can use this to compare with my notes. I attempted this question numerous times however, Im still having trouble understanding. Thank you.


The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek:<br>Performance Time<br>(seconds)<br>Task<br>Predecessors<br>A<br>24<br>B<br>28<br>A<br>14<br>A<br>D<br>15<br>A<br>В. С<br>D. E<br>E<br>12<br>30<br>This exercise only contains parts b. c. d, e, and f.<br>o) Given the demand, the cycle time for the production of the new train set = 32.0 seconds (round your response to one decimal place).<br>c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number).<br>d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)<br>Task<br>Workstation #<br>A<br>Station 1<br>В<br>Station 2<br>Station 3<br>D<br>Station 3<br>Station 4<br>

Extracted text: The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: Performance Time (seconds) Task Predecessors A 24 B 28 A 14 A D 15 A В. С D. E E 12 30 This exercise only contains parts b. c. d, e, and f. o) Given the demand, the cycle time for the production of the new train set = 32.0 seconds (round your response to one decimal place). c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number). d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # A Station 1 В Station 2 Station 3 D Station 3 Station 4
Were you able to assign all the tasks to the theoretical minimum number of workstations? No<br>e) The total idle time per cycle for the process = 27 seconds (enter your response as a whole number).<br>f) The efficiency of the assembly line with 5 workstations = 82.0% (enter your response as a percentage rounded to one decimal place).<br>If one used<br>workstations instead of 5, the efficiency of the assembly line would be = 68.3 % (enter your response as a percentage rounded to one decimal place).<br>Heln me solve this<br>Video<br>Get more help.<br>Similar questio<br>

Extracted text: Were you able to assign all the tasks to the theoretical minimum number of workstations? No e) The total idle time per cycle for the process = 27 seconds (enter your response as a whole number). f) The efficiency of the assembly line with 5 workstations = 82.0% (enter your response as a percentage rounded to one decimal place). If one used workstations instead of 5, the efficiency of the assembly line would be = 68.3 % (enter your response as a percentage rounded to one decimal place). Heln me solve this Video Get more help. Similar questio