SBM4201 System Analysis and Design XXXXXXXXXXPage 1 of 2 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: XXXXXXXXXX Group/individual: Individual Assignment...

1 answer below »
thats a portfolio i have more 4 similar to this word count is not applicable


SBM4201 System Analysis and Design Page 1 of 2 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 1 Group/individual: Individual Assignment Weighting: 10% Question one: Allhomes Company Case Study The IT department at the Allhomes company has received the approval to add new position of systems analyst. Your role is to support the set up the hiring timetable and tasks. After discussion with a number of employee in the department, you identified the tasks and the order in which they have to be performed as follows: First, review the applications (2 days). Then start three tasks: notify the IT team (1 days) and set up an interview schedule (5 days). When the team has been notified and the conference room reserves, prepare a set of interview questions (2 days). When the questions are ready, and the interview schedule has been developed, conduct the interviews (5days). After the interviews are done, meet with the hiring committee to select a candidate (1 day). Tasks: 1. Prepare a work breakdown structure explaining task, durations, and predecessor task. 2. Calculate the start and finish date for each task and determine the critical path. Question two: iTech Company Case Study The HR department at the iTech company offers a job position to Kim Jones. She will start the new job after three weeks. As an IT department member, you were asked to set up an orientation for her, including meeting with human resources, users, and the IT team. Tour at the company needs also to be organized. You suggested the following schedule: First, Kim have to meet with the human resources to learn about the company benefits and policies (3 hours). After finishing the meeting, she has to handle three tasks at once: she could tour the company offices (4 hours), meet with the users (3 hours), and work on the necessary paperwork (2 hours). Then, after meeting the IT manager and with all the paperwork completed, she would meet with the entire IT team for a brief introduction (1 hours). SBM4201 System Analysis and Design Page 2 of 2 Tasks: 1. Prepare a work breakdown structure explaining task, durations, and predecessor task. 2. Calculate the start and finish date for each task and determine the critical path.
Answered Same DayApr 22, 2020SBM4201

Answer To: SBM4201 System Analysis and Design XXXXXXXXXXPage 1 of 2 SBM4201 System Analysis and Design Semester...

Amit answered on Apr 30 2020
162 Votes
Title of the assignment:
Student’s name:
Professor’s name:
Course title:
Date:
Table of Content
s
1.    Question 1: Task 1: WBS for Allhomes Company    3
2.    Question 1: Task 2: Critical path with starting and finishing date calculations    3
3.    Question 2: Task 1: WBS for iTech Company    4
4.    Question 2: Task 2: Critical path with starting and finishing date calculations    5
1. Question 1: Task 1: WBS for Allhomes Company
The organization of project related activities by means of easily manageable sections is known as WBS (work break down structure). The desired WBS for Allhomes Company is as given below:
    Task number
    Task description
    Task duration in days
    Predecessor task number
    1.
    Application reviewing.
    2
    -
    2.
    Notification to members of team.
    2
    1
    3.
    Conference room reservation for interview process.
    1
    1
    4.
    Develop schedule of proposed interview
    5
    1
    5.
    Preparations regarding question set development for interview...