1- An R & D project has a list of tasks to be performed whose time estimates are a. Draw the Gantt Chart Table 8.11: Time Estimates for R & D Project Activity Activity Name To tm tp i (in days) 1-2 A...



1-   An R & D project has a list of tasks to be performed whose time estimates are




a. Draw the Gantt Chart


Table 8.11: Time Estimates for R & D Project<br>Activity<br>Activity Name<br>To<br>tm<br>tp<br>i<br>(in days)<br>1-2<br>A<br>4<br>6<br>8.<br>1-3<br>В<br>2<br>3<br>10<br>1-4<br>6<br>8<br>16<br>2-4<br>1<br>3-4<br>E<br>6<br>7<br>3-5<br>F<br>7<br>14<br>4-6<br>3<br>5<br>7<br>4-7<br>H<br>4<br>11<br>12<br>5-7<br>I<br>4<br>6.<br>6-7<br>J<br>2<br>10<br>

Extracted text: Table 8.11: Time Estimates for R & D Project Activity Activity Name To tm tp i (in days) 1-2 A 4 6 8. 1-3 В 2 3 10 1-4 6 8 16 2-4 1 3-4 E 6 7 3-5 F 7 14 4-6 3 5 7 4-7 H 4 11 12 5-7 I 4 6. 6-7 J 2 10