Suppose that the completion time of a project as a proportion of the maximum allotted time is a beta random variable with a = 3 and B = 3. What is the probability that the completion of the project...


Need help with this stat question


Suppose that the completion time of a project as a proportion of the maximum allotted time is a<br>beta random variable with a = 3 and B = 3. What is the probability that the completion of the<br>project will require less than 80% of the maximum allotted time?<br>

Extracted text: Suppose that the completion time of a project as a proportion of the maximum allotted time is a beta random variable with a = 3 and B = 3. What is the probability that the completion of the project will require less than 80% of the maximum allotted time?