Job 175
Job 178
Job 179
Balance 2/1
$13,790
$ 0
$0
Direct Materials
16,200
8,500
30,500
Direct Labor Cost
23,300
7,600
45,000
Machine Hours
400hrs.
300hrs.
2,000hrs.
Overhead is applied to jobs at the rate of $25 per machine hour. By February 28, Job 178 is the only one unfinished. The balance of Finished Goods on February 1 is $94,000 (consisting of Job 177). Jobs 177 and 179 are sold during February. Stutz sells its product at cost plus 40%.
Calculate the balance in Work-in-Process on February 28.