Step 1From the following data, hand draw a simple network diagram, and hand calculate (do not use software for this exercise) forward and backward pass and total float for the project.Step 2Hand draw (legibly) an ‘early start’ bar chart for the network as analysed.Step 3Hand draw (legibly) a ‘late start’ bar chart for the network as analysedStep 4Allocate resources from the data provided below, to each of these bar charts.Step 5Prepare a resource histogram for each of the early start bar chart and the late start bar chart.Step 6Make suggestions regarding how activities in the bar chart might be scheduled to ‘level’ resources