solve all questions
Suppose 5 processes A, B, C, D and E arrive at the times indicated, and each of them is executed for the amount of time specified in the table below:
Using Shortest Process Next (SPN) scheduling algorithm, determine the following:
(i). the finish time for each process.
(ii). the turnaround time for each process.
(iii). the normalized turnaround time for each process.
(iv). the mean turnaround time for all processes.
(v). the mean normalized turnaround time for all processes.