SITXHRM003 Learners Assessment Guide Assessment 1 BSBMGT617 Develop and implement a business plan RTO No: 21595 | CRICOS Code: 02634E BSBMGT617 Develop and implement a business plan Assessment 1 Page 1 of 8 ©Copyright Academia International 2019 Version 4 Approved by: B. Wade Assignment Coversheet Name: Student ID: Email Address: Class: Unit name: Unit Code: Assignment name: Student Declaration I declare that – a. The evidence I have submitted for assessment is my own work, and b. The evidence I have submitted for assessment has not been shared with other students, and I have taken all reasonable precautions to ensure that my work cannot be accessed by other students that may seek to submit my work as their own, and c. All of the sources of information used to prepare my work have been, or may be accurately cited, and d. I retain a copy of all my original for my own records, or for resubmission if required by Academia Australia, and e. I have read and understood Academia Australia’s policy regarding plagiarism, and I accept the right of Academia Australia to investigate suspected plagiarism, and to act in accordance with the policy and procedure I have read. Student Signature: __________________________________________ Date of Submission: ___ / /20 BSBMGT617 Develop and implement a business plan RTO No: 21595 | CRICOS Code: 02634E BSBMGT617 Develop and implement a business plan Assessment 1 Page 2 of 8 ©Copyright Academia International 2019 Version 4 Approved by: B. Wade Assessment Information  You must achieve a satisfactory outcome for each of the required criteria of this assessment to be deemed satisfactory for this assessment. You must achieve a satisfactory result for the assessments for this unit of competency to achieve a competent result for the unit. If one or more of the assessment results are not satisfactory, you will be Not Yet Competent for this unit.  You may follow the Assessment Appeals process in the Student Handbook (www.academia21.com) if you are not satisfied with: o the assessment result; or o the way an assessment was carried out by your trainer; or o the conditions or structure of the assessment The student handbook has the steps for reassessment if you receive a Not Yet Competent mark and do not want to appeal. Reasonable adjustment for assessment Where students have highlighted Language, Literacy and Numeracy issues reasonable adjustment to the assessment can be made. Should you receive a ‘Not Yet Competent’ or ‘Resubmit’ result for the assessment you will be given the opportunity to re-submit your assessment work with any amendments requested by your trainer. The adjustment may include actions such as: • Student demonstrating knowledge through verbal discussion to identify correct answers • Student demonstrating knowledge through applied skills • Allowing additional time relating to disability • Through consultation amending assessment timeframes • Assistance in the form of the training location to allow easier access • Accessing relevant equipment or aids to assist the student • Adjustments to the assessment methods to cater for any special needs (without effecting the integrity of the outcome) If a student requests or is identified as requiring reasonable adjustment to the training and assessment process a detailed training and assessment plan including timetables, notes regarding the required adjustments, and any related communications regarding the adjustments must be maintained in the students file. The RTO Manager must review and authorise any request for ‘reasonable adjustment’ to ensure that any adjustments and resulting outcomes are not affecting the integrity of the training and assessment process. Location of and completion timeframes for assessment The location of the assessment will depend upon the nature of the assessment. Assessments such as; role plays, in class activities, presentations and written tests / knowledge questions will be conducting in the classroom. The timeframes and due dates for these assessments, as well as any reports, projects or research assignments, are documented in the stage outlines. Stage outlines are handed out at the beginning of each term. http://www.academia21.com/ BSBMGT617 Develop and implement a business plan RTO No: 21595 | CRICOS Code: 02634E BSBMGT617 Develop and implement a business plan Assessment 1 Page 3 of 8 ©Copyright Academia International 2019 Version 4 Approved by: B. Wade Assessment 1 - Project – Business Plan This project consists of evaluating (if applicable) and plan and develop a business plan for your workplace or as determined by your trainer. This assessment is one form of assessment type that is used to collect evidence and will count towards gaining competence toward this unit. To demonstrate competence each question must be answered by the student. You will be required to complete other relevant assessment tasks for this unit. This project – requires you to plan for and develop a complete business plan. Essentials Requirements as outlined in the “Context of and specific resources for assessment in the TP for this unit”: Assessment must ensure:  Access to appropriate documentation and resources normally used in the workplace. You are required to use an existing business plan in your
Answered Same DayOct 21, 2021BSBMGT617Training.Gov.Au

Answer To: SITXHRM003 Learners Assessment Guide Assessment 1 BSBMGT617 Develop and implement a business plan...

Ishmeet Singh answered on Nov 03 2021
148 Votes
ProjectSchedule
    Create a Project Schedule in this worksheet.
Enter title of this project in cell B1.
Information about how to use this worksheet, including instructions for screen readers and the author of this workbook is in the About worksheet.
Continue navigating down column A to hear further instructions.    LORNE HOTEL UPGRADE PROJECT
    Enter Company Name in cell B2.    Company: Lorne Hotel
    Enter the name of the Project Lead in cell B3. Enter t
he Project Start date in cell E3. Pooject Start: label is in cell C3.    Project Lead:     Project Start:        Fri, 1/1/2021
    The Display Week in cell E4 represents the starting week to display in the project schedule in cell I4. The project start date is considered Week 1. To change the display week, simply enter a new week number in cell E4.
The starting date for each week, starting with the display week from cell E4, starts in cell I4 and is auto calculated. There are 8 weeks represented in this view from cell I4 through cell BF4.
You should not modify these cells.
Display Week: label is in cell C4.        Display Week:        1                Dec 28, 2020                            Jan 4, 2021                            Jan 11, 2021                            Jan 18, 2021                            Jan 25, 2021                            Feb 1, 2021                            Feb 8, 2021                            Feb 15, 2021                            Feb 22, 2021                            Mar 1, 2021                            Mar 8, 2021                            Mar 15, 2021                            Mar 22, 2021                            Mar 29, 2021                            Apr 5, 2021                            Apr 12, 2021                            Apr 19, 2021                            Apr 26, 2021                            May 3, 2021                            May 10, 2021                            May 17, 2021                            May 24, 2021                            May 31, 2021                            Jun 7, 2021                            Jun 14, 2021                            Jun 21, 2021                            Jun 28, 2021                            Jul 5, 2021                            Jul 12, 2021                            Jul 19, 2021                            Jul 26, 2021                            Aug 2, 2021                            Aug 9, 2021                            Aug 16, 2021                            Aug 23, 2021                            Aug 30, 2021                            Sep 6, 2021                            Sep 13, 2021                            Sep 20, 2021                            Sep 27, 2021                            Oct 4, 2021                            Oct 11, 2021                            Oct 18, 2021                            Oct 25, 2021                            Nov 1, 2021
    Cells I5 through BL5 contain the day number for the week represented in the cell block above each date cell and are auto calculated.
You should not modify these cells.
Today's date is outlined in Red (hex #AD3815) from today's date in row 5 through the entire date column to the end of the project schedule.                                28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    1    2    3    4    5    6    7
    This row contains headers for the project schedule that follows below them.
Navigate from B6 through BL 6 to hear the content. The first letter of each day of the week for the date above that heading, starts in cell I6 and continues through cell BL6.
All project timeline charting is auto generated based on the start and end dates entered, using conditional formats.
Do not modify content in cells within columns after column I starting with cell I7.    TASK    ASSIGNED
TO    PROGRESS    START DEADLINE     END DEADLINE        DAYS    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S    M    T    W    T    F    S    S
    Do not delete this row. This row is hidden to preserve a formula that is used to highlight the curren day within the project schedule.                             
    Cell B8 contains the Phase 1 sample title.
Enter a new Title in cell B8.
Enter a name to assign the phase to, if it applies for your project, in cell C8.
Enter Progress for...