Site Contract Price Cost Incurred Estimated Costs to Complete Billings on Contract Collections on Billings 1 5,000,000 3,750,000 5,000,000 5,000,000 7,000,000 1,000,000 4,000,000 900,000 900,000...


MOC Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below (image):



If the company records revenue
at a point in time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31?



A.
5,100,000
B.
500,000
C.
250,000
D.
100,00


Site<br>Contract Price<br>Cost Incurred<br>Estimated Costs to Complete Billings on Contract Collections on Billings<br>1<br>5,000,000<br>3,750,000<br>5,000,000<br>5,000,000<br>7,000,000<br>1,000,000<br>4,000,000<br>900,000<br>900,000<br>2,500,000<br>1,000,000<br>1,000,000<br>1,500,000<br>1,000,000<br>

Extracted text: Site Contract Price Cost Incurred Estimated Costs to Complete Billings on Contract Collections on Billings 1 5,000,000 3,750,000 5,000,000 5,000,000 7,000,000 1,000,000 4,000,000 900,000 900,000 2,500,000 1,000,000 1,000,000 1,500,000 1,000,000

Jun 09, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here