Project Charter Document
Project Charter
Project Charter Document
5/13/2018
Online Stud Farm Management System (OSFMS)
Project Overview & Description 2
Part 1: Measurable Organizational Value (MOV) 2
Area of Impact 2
Desired Value 3
MOV Metric 3
Timeframe for MOV 3
Summary of MOV 3
Part 2: Scope Management Plan 3
Project Scope 3
In Scope 3
Out of Scope 4
Project Management Methodology 4
Project Resources 5
Technological Requirements 5
Facilities 5
Part 3: Project Schedule 6
Work Breakdown Structure (WBS) 6
Project Activities & Duration 7
Gantt chart 8
Time-phased Budget 10
Part 4: Project Risk Analysis and Plan 11
Assumptions 11
Dependencies 11
Constraints 11
Risk Identification 11
Risk Assessment, Evaluation & Treatment 11
Part 5: Quality Plan 13
Verification Activities 13
Validation Activities 13
Part 6: Closure & Evaluation 13
Closure Checklist 13
Closure Evaluation Outline 14
References 15
Appendix 16
Annotated Bibliography 16
Project Overview & Description
The project is being carried out by Globex to develop and implement Online Stud Farm Management System (OSFMS) for the breeders, farmers, Stud Farm Managers, and other users associated with the stud farms.
Currently, there are manual activities that are carried out in the booking operations, payments, and management of these farms. OSFMS will replace these manual activities with their automated counterparts and will provide the end users with the benefits as faster booking, better quality of operations, full-time availability, and likewise.
The project will be carried out in a series of five phases as initiation, planning, execution, control, and closure.
Part 1: Measurable Organizational Value (MOV)
Area of Impact
Area
Rank
Impact
Strategic Changes
5
· Streamlining and organization of the business operations
· Motivation to the other stud farms and agricultural units to adopt to the similar strategy
Customer/End-Users
1
· Increased booking speed
· Non-stop service availability
Financial/Economic Structure
3
· Enhancement of revenues
· Improved market shares
Organizational
4
· Enhancement in quality
· Improved cost-effectiveness
Social
2
· Better breeder/farmer satisfaction
· Agricultural changes
Desired Value
· Better: Revenues, quality of services
· Faster: Booking speed
· Cheaper: Agricultural costs
· Do more: Services & Bookings
MOV Metric
Stakeholder Name
Expectation from project
Target
Breeder Groups & Farmers
Better and faster services and bookings
32% increase
Agricultural resources – officials and managers
Better processing speed
65% increase
Regulatory Bodies
Reduced costs
38% decrease
Project Client
Better market shares
45% improvement
Timeframe for MOV
The targets listed in the table above will be accomplished in a period of 95 days.
Summary of MOV
32% increase in bookings, 65% increase in processing speed, 38% decrease in the costs, and 45% enhancement in the market shares will be witnessed (Miller, 2008).
Part 2: Scope Management Plan
Project Scope
In Scope
· The resources will execute the information collection activities by carrying out the processes, such as group discussions, interviews, domain analysis, and e-surveys. The data sets will be analyzed using automated data analytics tools.
· The feasibility of the project will be evaluated using the automated tools on the technical and financial aspects.
· The project resources will carry out planning tasks and processes by planning and estimating the schedule and budget for the project along with the quality, risks, resources, and communication.
· The design for the automated system will be developed and the resources will also develop source code for the online stud farm management system.
· The system will be tested on the functional and non-functional aspects to ensure that there are no defects present in the final release.
· The database will be integrated and the system will also be implemented by the resources in the project team.
Out of Scope
· The members will not carry out any of the marketing, advertising, or distributing activities.
Project Management Methodology
There are numerous project management methodologies that have been developed. One such methodology defined by the Project Management Institute (PMI) is the Project Management Body of Knowledge (PMBoK). This is the methodology that provides the senior management and leadership with the project management guidelines using the ten knowledge areas and five processes groups. These groups include initiation, planning, execution, control, and closure. The ten knowledge areas cover scope, schedule, cost, quality, human resources, risks, communication, stakeholders, integration, and procurement management (Bilkent, 2016).
The methodology will be applied in this project on the basis of these five process groups and ten knowledge areas. The initial project activities, such as feasibility analysis and highlighting will be done in the first...