ASSESSMENT TASK 2: PROJECT BUDGET Task summary: You are the Project Manager of THE CUPNBAKE Project as per assessment 1. In this assessment you will be required to complete a four (4) week budget...

1 answer below »
See Templet and instructions file


ASSESSMENT TASK 2: PROJECT BUDGET Task summary: You are the Project Manager of THE CUPNBAKE Project as per assessment 1. In this assessment you will be required to complete a four (4) week budget allocating you total budget of $75,000.00 as closely as possible to what the project plan aligns to. What do I need in order to complete this assessment? Computer and Microsoft Office Access to the Internet for research Budget Template When do I do this task? This task may be done in your own time DUE DATE IS: Sunday 14th March @ 11:59pm. What do I need to SUBMIT: · Completed Project Budget – USE THE TEMPLATE PROVIDED · Assessment Cover Sheet What do I need to do if I get something wrong? If your assessor sees that you have not completed all parts of the task completely and satisfactorily, the details of resubmission will be outlined to you through the Canvas LMS through assessment feedback. Templates provided: · Project Budget HERE: · · Assessment Cover Sheet HERE: · · Task outline (same as this information) HERE: · (Please check your downloads folder for the template if it does not open straight away) Background/Operational Brief: (as per Assessment 1) CupNBake café is opening a new smaller store in Canberra and will be based in Manuka. You have 3 staff members to assist you throughout the project. ALLOCATED BUDGET TO COMPLETION AND HANDOVER: $75000.00 (AU) Task summary: You are the Project Manager of the Project outlined below and are to complete the project plan template as provided in detail. Timeline: 4 weeks Budget:$75000.00 (AU) You are to complete the provided Project Budget Template in detail for the following: · Weekly costings – according to the Project Plan · 4 weekly allocations to the total of $75000.00 The template provided has areas for you to add information to as applicable. This will change on a weekly basis – do not keep it the same each week. Budgeting is important but remember it is also estimating at this point of the project. Try to have money in reserve for the unexpected Be sensible with your amounts – research this to be accurate as possible (remember that hospitality often buys in bulk and therefore has large savings on items such as crockery/cutlery etc) IF it appears you are going to go OVER the budget – review your amounts to ensure you stay within the allocated amounts. At week 4 there is an area for notations of how you have made adjustments or corrections to the budget should you seem to be going OVER the budget. Use this. Remember: · You are the Project Manager · You are to view every aspect of the project that is required to getting the set up to the opening date for the Owner · You are to do external research to assist you in this project if you have no prior experience or hospitality knowledge BSBPMG522 Undertake project work_2021 Capital Collegewww.capital.edu.au BSBPMG522 ASSESSMENT 2 2021 – BUDGET PLAN Budget allocated for 4 week project in TOTAL: $75000.00 *You are required to list the items under each subheading that is required to be allocated* Do this weekly as it will CHANGE – do not put the same items across every week. Week 1: Item Quantity Amount/per: $ Subtotal $ Total: $ Opening balance: $75000.00 Wages: Administration: Equipment: Contractors: Miscellaneous: Closing Balance: $ WEEK 2: Carry Over your closing balance from week 1 to the opening balance of week 2 Item Quantity Amount/per: $ Subtotal $ Total: $ Opening balance: $ Wages: Administration: Equipment: Contractors: Miscellaneous: Closing Balance: $ WEEK 3: Carry Over your closing balance from week 2 to the opening balance of week 3 Item Quantity Amount/per: $ Subtotal $ Total: $ Opening balance: $ Wages: Administration: Equipment: Contractors: Miscellaneous: Closing Balance: $ WEEK 4: Carry Over your closing balance from week 3 to the opening balance of week 4 THIS IS YOUR FINAL PROJECTED WEEK FOR THE BUDGET. ENSURE YOU ARE ON TRACK AND NOT OVER BUDGET. IF YOU ARE THEN ADDRRESS IT WITH APPROPRIATE NOTATIONS (bottom of table) ON WHAT HAS BEEN AMENDED TO REMAIN WITHIN BUDGET. Item Quantity Amount/per: $ Subtotal $ Total: $ Opening balance: $ Wages: Administration: Equipment: Contractors: Miscellaneous: Closing Balance: Notations for Budget reporting/corrections: 2
Answered 7 days AfterMar 12, 2021BSBWOR501Training.Gov.Au

Answer To: ASSESSMENT TASK 2: PROJECT BUDGET Task summary: You are the Project Manager of THE CUPNBAKE Project...

Tanmoy answered on Mar 13 2021
151 Votes
BSBPMG522 ASSESSMENT 2 2021 – BUDGET PLAN
Budget allocated for 4 week project in TOTAL: $75000.00
*You are required to list the items und
er each subheading that is required to be allocated*
Do this weekly as it will CHANGE – do not put the same items across every week.
Week 1:
    Item
    Quantity
    Amount/per: $
    Subtotal $
    Total: $
    Opening balance:
    
    $75000.00
    Wages:
    
    
    
    
    3 Staffs
    3
    $625/ per week
    $2500
    
    
    
    
    
    
    
    
    
    
    
    Administration:
    
    
    
    
    Location Rent
    1
    $500/ per week
    $500
    
    
    
    
    
    
    Equipment:
    
    
    
    
    Industrial Coffee Grinder
    2
    $6000
    $12000
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    Contractors:
    
    
    
    
    Plumbers
    2
    $800/ week
    $1600
    
    
    
    
    
    
    
    
    
    
    
    Miscellaneous:
    
    
    
    
    Cafe Lighted Sign Board
    1
    $250
    $250
    
    
    
    
    
    
    Total Cost
    
    
    
    $16850
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    Closing Balance:
    
    $58150
WEEK 2: Carry Over your closing balance from week 1 to the opening balance of week 2
    Item
    Quantity
    Amount/per: $
    Subtotal $
    Total: $
    Opening balance:
    
    $58150
    Wages:
    
    
    
    
    Wait staff
    3
    $300/ per week
    $900/ per week
    
    
    
    
    
    
    
    
    
    
    
    Administration:
    
    
    
    
    Concept and architectural...
SOLUTION.PDF