In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)
Extracted text: Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2022 $2,450,000 2,450, 000 2,350,000 2,300,000 2021 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,100,000 4,900, 000 $2,695,000 2,200,000 1,900,000 5,450,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Balance Sheet (Partial) 2021 2022 Current assets: Current liabilities: