Remington Construction Company uses the percentage-of-completion method. During 2020, the company entered into a fixed-price contract to construct a building for Sherman Company for P30,000,000. The...

What was the amount of construction costs incurred during 2021?Remington Construction Company uses the percentage-of-completion method. During 2020,<br>the company entered into a fixed-price contract to construct a building for Sherman Company<br>for P30,000,000. The following details pertain to the contract:<br>At December 31, 2020<br>At December 31, 2021<br>Percentage of completion<br>25%<br>60%<br>Estimated total cost of contract<br>P22,500,000<br>P25,000,000<br>Gross profit recognized to date<br>1,875,000<br>3,000,000<br>The amount of construction costs incurred during 2021 was<br>

Extracted text: Remington Construction Company uses the percentage-of-completion method. During 2020, the company entered into a fixed-price contract to construct a building for Sherman Company for P30,000,000. The following details pertain to the contract: At December 31, 2020 At December 31, 2021 Percentage of completion 25% 60% Estimated total cost of contract P22,500,000 P25,000,000 Gross profit recognized to date 1,875,000 3,000,000 The amount of construction costs incurred during 2021 was

Jun 09, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here