Refer to the activity network table shown in Exercise XXXXXXXXXXSuppose that we modified the original table slightly to show the following predecessor relationships between tasks and resources...

Refer to the activity network table shown in Exercise 12.23. Suppose that we modified the original table slightly to show the following predecessor relationships between tasks and resources assigned to perform these activities. Enter this information into MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/ day or 40 hours/week) basis.





a. Using the Resource Usage view, can you determine any warning signs that some member of the project team has been overassigned?


b. Click on the Task Usage view to determine the specific days when there is a conflict in the resource assignment schedule.